Menu
Hastings & St. Leonards on-line community newspaper

Sea Change plans to install traffic lights at the junction between Junction Road and the A21 just below The Ridge.

Questions ESCC needs to answer about Queensway Gateway project

Sea Change Sussex’s Queensway Gateway Road project is not due to come up at the South East Local Enterprise Partnership’s accountability board until March, but important questions have arisen for ESCC as to who is responsible for completing it and for paying for it. The council refuses to comment. Meanwhile another director has resigned from the Sea Change board. Nick Terdre reports.

The fate of the Queensway Gateway Road remains undecided ahead of the meeting of the South East Local Enterprise Partnership’s accountability board in March. (The board meets in late January but not to discuss Local Growth Fund (LGF) projects like this one).

Judging by the lack of progress at last year’s meetings, it would not be advisable to imagine that either the board or the public will be much better informed about when the road is likely to come into operation by the time of the next meeting.

That is down to East Sussex County Council, which, as the accountable body for grants and loans advanced to projects in its area, is responsible for keeping Selep informed on project progress and any problems which arise.

Indeed it is more likely that the outstanding technical arrangements, including a traffic regulation order, to be agreed between Sea Change Sussex, the contractor, East Sussex County Council, the scheme promotor, and the Highways Authority will be settled by then than key questions such as who is responsible for completing the road and who will pay for the final works.

And possibly the deep-dive investigation being conducted by the Department for Levelling Up, Housing and Communities into Sea Change projects funded by Selep and overseen by ESCC will be completed by then.

Until a few months ago it seemed clear enough that Sea Change was responsible for both finishing the road and providing the balance of £2m to pay for the work. Although the budget for the project had yo-yo’d wildly, from £15m when the business case was approved, down to £6m and then up to £12m, Sea Change had built most of the road, in the process spending £10m from Local Growth Fund monies made available by Selep.

Then its plan to build the final section connecting with Sedlescombe Road North (the A21) – over land occupied by the Bartlett car dealership just below The Ridge – ran into a brick wall, obliging the company to come up with the alternative plan of linking the road into Junction Road and installing traffic lights where Junction Road interconnects with the A21.

Bartlett’s SEAT showroom beside the A21, through which Sea Change planned to link the Queensway Gateway Road to the A21.

Alternative version

But in September last year Sea Change started putting out an alternative version of how things stood, concluding that it had fulfilled its undertakings on the project to ESCC, was not liable to fund the remaining works and would only undertake these if someone else came up with the funding.

ESCC owes both Selep and the public an explanation of where it stands, but its reports to Selep have virtually nothing to say about these matters, and in response to HOT’s detailed enquiries it merely responded: “We’re extremely keen to see completion of the Queensway Gateway Road and discussions are ongoing with Sea Change.”

Sea Change used a question to the accountability board in September to claim that it was not responsible for ESCC’s report to Selep in November 2015 that the budget had been reduced to £6m. “The reduced figure did not come from Sea Change Sussex and, contrary to what the Selep report says, Sea Change did not think the project could be delivered for £6m,” it told HOT in October.

Its argument is that the budget for the road in the business case was £15m, of which it has only received £10m. “The grant was intended to cover delivery of the whole project as laid out in the approved business case: a completed road for a total budget of £15m. Our grant agreement refers to that project and business case. We’ve so far received £10m of this funding and have completed works in line with this sum,” it said.

In October it further stated that: “Our grant agreement [with ESCC] requires us to complete the funded works — which we’ve done. It contains no obligation for us to deliver further elements of the project unless we enter into an additional agreement to do so, with funding to cover that.”

This raises questions about its contract with ESCC, which should mirror ESCC’s contract with Selep (or more specifically with Essex County Council which acts as the accountable body to Selep for supervising grants and loans made to Selep’s member councils): while ESCC is responsible to Selep for delivering the project in accordance with the business case, the contractor is responsible to ESCC for the same.

But when asked if its agreement with ESCC mirrored ESCC’s service level agreement with Essex County Council, Sea Change said it did not.

Serious implications

Sea Change’s claims have serious implications for ESCC. It would be in hot water, for example, if it had made a false report to Selep about the budget being reduced, especially as this was the basis for seeking to have the surplus grant monies transferred to another Sea Change project, the North Bexhill Access Road.

On this issue ESCC has previously told HOT: “We’re extremely keen to see completion of the Queensway Gateway Road and we have no reason to think partners have been given inaccurate information about the project.”

But it is hard to see how its report to Selep can be squared with Sea Change’s version of events.

Of course there is scepticism over Sea Change’s claims. Could it really have remained in ignorance of what was happening to the Queensway Gateway budget, and especially when in February 2018 ESCC reported to Selep that various costs had increased and the road would now cost £12m rather than £6m? After all, chief executive John Shaw was present at the meeting when this report was discussed.

On this occasion Selep agreed to transfer £4m from other LGF projects (including £3m from the Hastings and Bexhill Movement and Access Package). Of the balance of £2m, the agenda pack notes, “In addition, Sea Change East Sussex, as project delivery partners, will be contributing up to £2m to support the completion of the project.”

Of the company’s “contribution,” Sea Change’s version, as told to HOT, is that: “We offered, if needed, to provide £2m to bridge a cash flow gap in the funding, subject to certain conditions and on the understanding that it would be repaid from the total approved £15m funding when more monies became available.”

In September the ESCC report to the board started referring to the outstanding balance as “temporary contingency funding.” It neither flagged up the change nor explained what was meant by this phrase, but all parties understand that Sea Change’s position is that the £2m will not be coming from its coffers.

So Sea Change has provided its version of where the Queensway Gateway Road project stands, but what of ESCC? It has yet to account for itself.

Omissions

These matters are not raised in the ESCC officer’s update on the project for the accountability board’s November meeting, which, while going into extensive details on the travails to get the necessary technical approvals for completing the road, says of the funding issue only that: “Ongoing discussions between Sea Change Sussex and East Sussex County Council continue on the overall funding package and confirming the contractual position to be applied for the delivery of the connection to the A21,” and nothing on Sea Change’s position concerning the other matters.

As Helen Dyer, Selep’s capital programme manager commented, “The report does not provide a detailed update on the confirmed funding package and, as a result, does not provide any additional information in relation to the status of the Sea Change Sussex funding contribution which has been labelled as ‘temporary contingency funding’.”

This surely should have been a prompt for the accountability board to require accountability. Answers could have been required from board member Cllr Keith Glazier, the ESCC leader and vociferous champion of Sea Change’s work. But beyond acknowledging that the funding issue needed clarifying, the board showed no curiosity in seeking to clarify why Sea Change was putting forward its alternative narrative and what this implied for the integrity of ESCC’s reporting to Selep.

Perhaps they are awaiting the results of the audit that Selep chief executive Adam Bryan told a questioner in September would be conducted into projects which have received funding through the partnership’s capital programme.

If Selep is unable or unwilling to throw light on ESCC’s dealings with Sea Change, it will be up to the council’s Place Scrutiny Committee when it meets to consider this matter on 28 March.

ESCC taxpayers deserve a response from their council. £10m may be at stake – the value of the grant that would have to be returned to government if the road is not completed in accordance with the terms of the its approval. If the liability does not lie with Sea Change, as the company asserts, it would fall to ESCC to repay it, at its taxpayers’ expense.

Board member resigns

Richard Garland, a representative of the Hastings, Bexhill and East Sussex Business Association (HBESBA), resigned from the Sea Change Sussex board in December, for what he told HOT were “personal reasons.” HBESBA wields in effect a controlling share of 50% of the votes.

Garland has also resigned from the association, leaving it with only three directors listed at Companies House, two of whom are Sea Change directors, including Sonia Blizzard, the company’s chair.

HBESBA, which has no online presence beyond its listing at Companies House, is registered at the Innovation Centre, Highfield Drive in St Leonards, where Sea Change has its headquarters, but has no office there.

A spokesperson for the association told HOT that its “purpose is to be a member of Sea Change Sussex, with the association’s members sitting on the Sea Change Sussex board as volunteers to bring the perspective and experience of members of the local businesses community to guide the economic development programme.”

On the question of whether local companies could join the group, the spokesperson said, “Other businesses could potentially join in future, although the association is quorate and its board hasn’t felt the need to add any additional members to date.”

The board would in due course consider whether to appoint another director to take Garland’s place, HOT was told.

Two of the directors representing councils resigned from the Sea Change board last year — Cllrs Kevin Dixon and Paul Barnett of Rother District Council and Hastings Borough Council respectively. Cllr Nick Bennett of East Sussex County Council remains on the board, and all three councils remain affiliated to the company.

If you’re enjoying HOT and would like us to continue providing fair and balanced reporting on local matters please consider making a donation. Click here to open our PayPal donation link. Thank you for your continued support!

Posted 12:27 Saturday, Jan 21, 2023 In: Point of View

10 Comments

Please read our comment guidelines before posting on HOT

  1. Chris Sharpe

    It’s appalling that nothing’s been done for years to complete this project. Given that £10m has already been spent, and congestion in the area remains, I suggest that the ratepayers who are on the hook for the repayment by ESCC of that £10m (if the project isn’t completed) should tell ESCC to accept Sea Change’s proposal very rapidly, and find the funding to complete the project. How the original £15m funding was somehow reduced to £6m is irrelevant now. All the parties involved seem to have been at fault, but ESCC must now get a grip and resolve the funding issue the final works. The alternative is totally unacceptable.

    Comment by Chris Sharpe — Wednesday, Jan 31, 2024 @ 13:48

  2. ted

    Millions? 2 or 3 mini roundabouts would have solved this using the existing roads. A few signs and a bit of white paint.

    Comment by ted — Thursday, Sep 7, 2023 @ 08:49

  3. Zoe

    I can’t believe after all these years this bottleneck into Hastings still exists.

    Comment by Zoe — Thursday, Sep 7, 2023 @ 01:17

  4. Harry

    I’ve given up worrying about this mess. All the “authorities” responsible are clearly populated by lazy incompetent bureaucrats who hide behind long words and just blame each other. Sack the lot of them.

    Comment by Harry — Saturday, Jan 28, 2023 @ 18:56

  5. Anna Sabin

    If cars are to make way for walking, cycling and bus route networks, the motor-dedicated road network will need to be as joined up as possible. Smoothly connecting the A2690 to the A21 would contribute to that. ESCC have no such coherent plan, they are still permitting and building for ‘cars everywhere’. In the process they’re destroying bluebell woods and churning out consultation reports on active and public transport with lashings of greenwash without actually building any of it.

    Comment by Anna Sabin — Thursday, Jan 26, 2023 @ 14:23

  6. H. Grigg

    I agree with I Tomisson
    ESCC and all those associated with the this complete farce should be accountable for :-
    1. The brief
    2. The budgets
    3. Timing
    On none of those have they demostrated that the can deliver, whether politcally or otherwise.
    The residential and business communities have been woefully let down.
    H. Grigg
    8 Park Wood Road,
    Hastings TN34 2RW
    01424 584 891

    Comment by H. Grigg — Tuesday, Jan 24, 2023 @ 15:03

  7. Ian

    How about making some money back by charging parking fees on it at least? Seems to me the local companies love it, free parking for huge lorries and cars! You built them a car park and vehicle storage facility, at least cash in on it!

    Comment by Ian — Monday, Jan 23, 2023 @ 12:47

  8. I Tomisson

    This shambles should be referred to the National Audit Office to investigate.

    Comment by I Tomisson — Monday, Jan 23, 2023 @ 09:55

  9. ken davis

    To be honest, it’s about time there was a full public inquiry into all the operations of Seaspace/Seachange including the policy of building lots of empty office blocks.

    Comment by ken davis — Monday, Jan 23, 2023 @ 08:26

  10. Emily Johns

    A simple solution to this fiscal fiasco would be to leave well alone. In 2016 there was the bluebell-filled Hollington Valley Nature Reserve where the Queensway Gateway road stump now stands. Allowing the natural regeneration of the meadows and woodland in the Valley and reallocating money that might be used on finishing this road to improving cycling, walking and public transport infrastructure would show that East Sussex County Council was serious about addressing climate change and species loss.

    Comment by Emily Johns — Sunday, Jan 22, 2023 @ 22:33

Leave a comment

(no more than 350 words)

Also in: Point of View

«
»
More HOT Stuff
  • SUPPORT HOT

    HOT is run by volunteers but has overheads for hosting and web development. Support HOT!

    ADVERTISING

    Advertise your business or your event on HOT for as little as £20 per month
    Find out more…

    DONATING

    If you like HOT and want to keep it sustainable, please Donate via PayPal, it’s easy!

    VOLUNTEERING

    Do you want to write, proofread, edit listings or help sell advertising? then contact us

    SUBSCRIBE

    Get our regular digest emails

  • Subscribe to HOT